Oct 7 (Reuters) - Western Areas Ltd WSA.AX :
* Western Areas revised FY 2016 capital expenditure plans
* Says production guidance on both cost and volume and associated mine plans remain unchanged
* Says sustaining capital expenditure, mainly in mine development, down $11.0M
* Amended capital expenditure profile does not change the current mine plans and has no impact on production or unit cost forecasts
* Says cosmos feasibility and exploration expenditure reduced by $3.0M to $4.0M
* Western areas' production guidance also remains unchanged, for both unit cost and expected nickel volume
* Says forrestania and regional exploration expenditure reduction of $4.0M
* The capital expenditure profile for the operations will now be smoothed over the next 20 months