SANTIAGO, Feb 21 (Reuters) - Chile's Escondida copper mine, the world's largest, said on Tuesday it would not begin replacing striking workers for at least 30 days into the work stoppage to show its commitment to dialogue.
The mine can legally hire temporary workers after 15 days of a strike. Tuesday marked 13 days since unionized workers walked off the job at Escondida, which is controlled by BHP Billiton BHP.AX BLT.L .
Waiting to replace workers means there will be no production from Escondida for at least another two weeks if the strike continues. That will likely push copper prices CMCU3 , which have already hit 20-month highs on supply concerns, even higher.
Government-mediated talks on Monday failed to get workers and representatives of the mine to commit to a schedule of new wage talks. company and union are far apart on a number of issues, including shift pattern changes, the size of a one-time bonus, and BHP's wish to give new workers lower benefits.
It was unclear for days if the meeting would even take place as BHP blamed striking workers for interfering with non-unionized service employees on their shift changes.
Escondida is majority-controlled by BHP with minority interests held by Rio Tinto RIO.AX RIO.L and Japanese companies including Mitsubishi Corp 8058.T. The mine produced about 5 percent of the world's copper in 2016.