💥Fed cuts sparks mid cap boom! ProPicks AI scores with 4 stocks +23% each. Get October’s update first.Pick Stocks with AI

Tlou Energy provides update on construction of power transmission line for plant at Lesedi in Botswana

Published 13/09/2022, 06:05 pm
© Reuters.  Tlou Energy provides update on construction of power transmission line for plant at Lesedi in Botswana

Tlou Energy Limited provided an update on the construction of a power transmission line for its coal bed methane (CBM) extraction and power generation plant at Lesedi, west of Serowe in Botswana.

Tlou said overall progress achieved is currently 11% which is up from 8% reported last month, although the planned target was 17% indicating a slippage of 6%.

A 66 kilovolt (kV) transmission line and associated substations will connect the plant to the Botswana Power Corporation (BPC) grid at Serowe. The grid connection project is divided into two project parts; (i) the 66kV overhead transmission line, and (ii) the substation works at both ends of the line.

The 66kV transmission line construction contract between Tlou and Zismo Engineering was awarded on March 2, 2022, and commenced in April. The contract is expected to take approximately 15 months to complete, the company said.

The substation works tender has been awarded to OptiPower, a division of Murray & Roberts Ltd. The substation contract has not yet been signed and will be done once additional funding is in place, it added.

Progress to date:

  • Line survey is 96% complete. The remainder relates to the steel pole section.
  • Bush clearing is at 60%, delayed but without impact on program.
  • Line pegging and inspection at 50%. Delays incurred because of other services on the servitude (right of way) such as water pipelines and crossing low voltage powerlines. All being attended to.
  • Pole dropping at required locations along the route is at 42%.
  • Pole dressing (adding required equipment to poles) is only partially complete because of delays in delivery of U-bolts.
  • Discussions were required with BPC in relation to an 11kV line that has been built across the Tlou 66kV servitude. BPC have proposed to move their line out of the servitude. This work is not expected to cause a delay as it can be completed while other parts of the project are ongoing.
Tlou said a requirement to add pole savers (to provide added protection) to the wooden poles at the request of BPC was at the discretion of the engineer and had not been raised as an issue during the planning, design and procurement stages of the project. This will delay the planting of poles, it noted, and said procurement has also suffered delays with line hardware manufacturing resulting in delays to commence pole dressing and planting.

The slippage to date may be recovered in the coming months, the company noted. Procurement and other issues outside the company's control could delay the project further which will be advised in further updates if necessary, however, it said, at this time the transmission line section should remain close to the target completion date of mid-2023.

The Lesedi Power Project is located in Botswana's Central District, approximately 100 kilometres (km) from the existing electricity grid. The 66kV line being constructed will be capable of carrying up to 25MW of power. Initial electricity generated will be sold to Botswana Power Corporation, the national power utility under an agreed 10MW Power Purchase Agreement (PPA).

Tlou has been producing gas at its Lesedi 3P and Lesedi 4P production wells. The company has taken the decision to temporarily shut in the Lesedi 3P well as sufficient data exists from this well and there is no need to incur further production costs at this time. The well can be brought back into production as required. Gas production at Lesedi 4P is planned to continue.

In early trade on Tuesday, Tlou shares were 3.5% higher at 1.50p.

Read more on Proactive Investors AU

Disclaimer

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.