April 7 (Reuters) - Aurizon Holdings Ltd AZJ.AX :
* Aurizon network operational update - cyclone debbie
* Blackwater system was expected to re-open in week ending sunday, 9 april
* Blackwater system will now re-open to coal traffic on monday 10 april
* Aurizon has mobilised all available crews and resources, including contractors, to undertake repairs across four coal systems
* Newlands system is expected to re-open on friday, 14 april
* Moura system is now expected to re-open on wednesday, 12 april
* "network is expected to operate under restricted conditions with some reduced capacity"
* Repairs to large sections of infrastructure of Goonyella system at black mountain are scheduled to be completed by 11 april Source text for Eikon: Further company coverage: AZJ.AX