Oct 28 (Reuters) - Newcrest Mining Ltd NCM.AX :
* Cadia concentrator 1 sag mill remains offline NCM.AX
* Says inspection has revealed more loose windings than initially anticipated
* Says is anticipated that construction will take around 6 weeks
* Says a repair and remediation plan is currently being developed
* Says in the interim the concentrator 1 sag mill will remain offline for at least the next 5 weeks
* To reduce impact on production conveyor is being installed to transport ore from high pressure grinding rolls to ball mill circuit, bypassing concentrator 1 sag mill
* It is anticipated that construction will take around 6 weeks"
* Says "it is too early to define any impact on FY 2016 production and cost guidance"
* Refers to problem detected with motor on concentrator 1 sag mill
* Concentrator 2 Sag mill continues to operate at full capacity with ore from cadia east being trucked to this mill"