Zimbabwe platinum mines to ride out power cuts, gold output less secure

Published 15/05/2019, 10:34 pm
© Reuters.  Zimbabwe platinum mines to ride out power cuts, gold output less secure

* Zimbabwe suffering blackouts of up to 10 hours daily

* Platinum producers able import extra power if needed

* Gold miners have to rely on grid or expensive generators

* Mining generated most of Zimbabwe's 2018 export earnings

By MacDonald Dzirutwe

HARARE, May 15 (Reuters) - Power imports are cushioning platinum mining companies against Zimbabwe's worst blackouts in three years, but gold mines could face production cuts as they continue to rely on an unstable national grid, industry officials said.

State utility ZETDC this week started indefinite rolling power cuts lasting up to 10 hours per day, blaming low water levels at the dam that supplies the biggest hydro plant and creaking infrastructure at ageing coal-fired generators.

Mining generated most of Zimbabwe's $4.8 billion of export earnings last year and the cuts have raised the risk of further damage to an economy already experiencing a severe dollar crunch, soaring inflation and shortages of fuel and medicines.

In 2016, during the worst daily blackouts in decades that lasted up to 18 hours, output at most gold mines was affected.

Zimbabwe Electricity Transmission and Distribution Company (ZETDC) at that time asked producers to pay more to guarantee uninterrupted supplies.

Three years later, with Zimbabwe producing 969 megawatts of power daily against peak demand of 2,100 MW, the industry appears better prepared, and the blackouts have had no measurable impact on either platinum or gold prices.

However, officials say gold miners may again face higher costs this time and may need to fall back on expensive diesel generators to keep production going.

3rd party Ad. Not an offer or recommendation by Investing.com. See disclosure here or remove ads .

Meanwhile, some new mining projects are looking to become less tied to the grid by installing renewable energy sources.

PLATINUM PREPARED

The two largest platinum producers, Anglo American (LON:AAL) Platinum AMSJ.J and Impala Platinum IMPJ.J , said power supplies for their Zimbabwe operations were secure. Implats owns Zimplats ZIM.AX while Amplats runs the smaller Unki Mine.

An Implats spokesman said Zimplats had secured power from Mozambique and a deal to use Zimbabwe's transmission network to deliver it.

Zimplats, which produced 66,495 ounces of platinum in the quarter to March, listed power supply among major risks in its 2018 report. It did not say how much it spent on power imports last year.

Amplats said its 85,900 ounces a year Unki mine had no doubt that ZETDC would deliver uninterrupted electricity but that, should it become necessary, "Unki would be allowed to source the supply of electricity externally."

Zimbabwe is the world's no. 3 platinum producer, but patchy power supplies have stopped the industry from building a local refinery and it continues to ship unrefined platinum to South Africa.

Producers have invested in power substations and helped ZETDC maintain transmission lines to guarantee supplies, but they also have the economic muscle to import electricity using their dollar earnings.

"MASSIVE HIT"

Zimbabwe's mostly small-scale gold miners, which produced a record 996,373 ounces last year, are however still dependent on national grid and said any power cuts would affect production.

Demand Gwatinenga, general manager at How Mine, one of the country's biggest and oldest, said it may need to rethink its decision last year to stop paying a higher ring-fenced electricity tariff that had become too expensive.

3rd party Ad. Not an offer or recommendation by Investing.com. See disclosure here or remove ads .

"It might make sense to go back to (it)... with the hope that it guarantees supplies. Any interruption ...will be a massive hit for us, we can't afford it," he said Gwatinenga, adding that ZETDC had not indicated if it would cut power to the mine.

Mark Learmonth, chief financial officer of London-listed Caledonia, which owns Blanket gold mine in western Zimbabwe, said it still paid an 83% premium on the normal tariff to avoid power cuts. Even so, supply had been unstable, and there could be up to six outages of 45 minutes each in a 12-hour shift.

"We have back-up diesel generators but given the increased scale of our operations we now need to add further capacity," Learmonth told Reuters, adding that diesel supply might be harder to come by due to rising demand from South Africa, suffering a power crisis of its own.

Blanket, which produced 69,463 ounces of gold last year, did not have the capacity to import power directly, he said.

Some new mining projects are looking at alternative power sources. South Africa's Tharisa Resources, which holds a 26.8 percent in Karo Resources - planning a $4.2 billion platinum project in Zimbabwe - said Karo would build a 300 MW solar plant.

"Once the approvals have been signed off, the first phase of around 50 megawatts would take around 12 months to be fully operational," Tharisa CEO Phoeovos Pouroulis told Reuters.

Zimbabwe's biggest chrome miner, African Chrome Fields, said it was using diesel to power its operations and would not be affected by the cuts.

3rd party Ad. Not an offer or recommendation by Investing.com. See disclosure here or remove ads .

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.