UPDATE 2-Rio Tinto confirms $6.75 bln cost for Mongolia mine, production to start late 2022

Published 16/12/2020, 07:06 pm
RIO
-
RIO
-
HG
-
TRQ
-

(Recasts, adds analyst comment)

Dec 16 (Reuters) - Global miner Rio Tinto (LON:RIO) RIO.AX said on Wednesday the underground expansion at its Oyu Tolgoi copper mine in Mongolia would cost $6.75 billion, as it remained at odds with its majority-owned Turquoise Hill Resources TRQ.TO over funding for the mine.

Oyu Tolgoi is one of the world's largest-known copper and gold deposits, located in the South Gobi region of Mongolia. The Mongolian government holds a 34% stake in the project, and Rio-controlled Turquoise Hill TRQ.TO owns the rest.

The project was held up as Mongolia sought to strike a better bargain, with Rio and Turquoise locked in a feud over the expansion's funding, and costs ballooning because of the difficult geology of the site. said Wednesday progress on funding has been "limited" and reiterated that it "remains of the view that all shareholders should contribute proportionately" to mine development.

The miner said expansion of the first section of the underground zone would achieve sustainable production by October 2022. Costs accounted for the expected impact from COVID-19, it said.

"Overall, we view the update as positive for TRQ (Turquoise Hill) shares given the slightly lower capex," Scotiabank analyst Orest Wowkodaw told clients.

Turquoise Hill had previously pegged costs for the mine extension around $6.85 billion. Its shares were up slightly at C$15.13 by mid-morning.

Rio said Oyu Tolgoi is expected to produce 480,000 tonnes of copper per year on average from 2028 to 2036 from both the open pit and underground mine, against 146,300 tonnes in 2019 from just the open pit.

By 2030, Oyu Tolgoi is expected to be the fourth-largest copper mine in the world, the company said.

The miner said the next two sections of the underground mine, which would support a ramp-up to 95,000 tonnes of ore per day, were still being studied, with initial recommendations expected by mid-2021.

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.