Mongolia says can build power plant to supply Oyu Tolgoi mine

Published 21/02/2018, 03:37 am
Updated 21/02/2018, 03:40 am
Mongolia says can build power plant to supply Oyu Tolgoi mine

* Tensions running high over tax bill

* Rio Tinto , Turquoise Hill say are assessing options

By Terrence Edwards

ULAANBAATAR, Feb 20 (Reuters) - Mongolia can build a power plant at its Tavan Tolgoi coal mine by 2021 to supply the Oyu Tolgoi copper project, energy officials said on Tuesday, as the government seeks to hold Rio Tinto RIO.AX RIO.L to an agreement to use Mongolian power.

Tensions have mounted between the Mongolian government and its fellow shareholders in Oyu Tolgoi, where Rio Tinto is operating a huge underground extension.

Last week, Rio Tinto said it was working with its partners to find a solution after the government announced the cancellation of a contract, which Rio interpreted as meaning the Tavan Tolgoi power project was no longer viable. Energy Minister Tserenpil Davaasuren said on Tuesday a cooperation agreement with a party called South Gobi Energy had been cancelled, but a plant at the Tavan Tolgoi coal mine was still in development.

Oyu Tolgoi had "the responsibility to choose total energy demand for Oyu Tolgoi from Mongolia within four years," he said.

D. Batbileg, director of the Tavantolgoi Power Plant Project, addressing the same news conference said construction work was "ready to begin".

Local media reported the government was seeking guarantees from Rio Tinto before going ahead.

Rio Tinto was not immediately available to comment. Its statement last week said it was working on all options, including the construction of a power plant at Oyu Tolgoi whose cost would be finalised between shareholders.

3rd party Ad. Not an offer or recommendation by Investing.com. See disclosure here or remove ads .

The mine is jointly owned by the government of Mongolia, with 34 percent, and Turquoise Hill Resources TRQ.TO with 66 percent. Turquoise Hill is in turn 51 percent-owned by Rio Tinto.

Turquoise Hill also said it was evaluating its options.

"A final decision on the outcome, cost or financing of a permanent domestic power supply has not been concluded at this time," an emailed statement said.

Tensions over tax and benefits to the country held up an expansion project for underground mining to tap into most of the resource in 2013. Construction resumed after May 2015, when the parties signed a new agreement.

But the international partners are again at odds with the government following a claim from the Mongolian Tax Authority for an additional $155 million for the years 2013 through 2015. and addition reporting by Barbara Lewis; Editing by Mark Potter)

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.