Nov 12 (Reuters) - OZ Minerals Ltd OZL.AX :
* TARGET DATE FOR 1ST SALEABLE CONCENTRATE PRODUCTION FOR CARRAPATEENA COPPER GOLD MINE POSTPONED FROM NOVEMBER TO DECEMBER
* REVISED TIMING IS DUE TO INCORRECT VENDOR SUPPLIED ITEMS ASSOCIATED WITH MINERALS PROCESSING PLANT
* PROJECT DEVELOPMENT COST OF CARRAPATEENA AT FIRST CONCENTRATE IS NOW EXPECTED TO BE IN RANGE OF $950 - $980 MILLION
* 2019 PRODUCTION GUIDANCE FOR CARRAPATEENA OF 2,000-4,000 TONNES OF COPPER AND 3,000 TO 6,000 OUNCES OF GOLD HAS BEEN REMOVED