Jan 28 (Reuters) - Fortescue Metals Group Ltd FMG.AX :
* GUIDANCE FOR FY21 SHIPMENTS, C1 COST AND CAPITAL EXPENDITURE REMAINS UNCHANGED
* QTRLY TOTAL ORE SHIPPED 46.4 MT VERSUS 46.4 MT
* QTRLY ORE MINED 50.0 MT VERSUS 54.6 MT
* QTRLY ORE PROCESSED 44.2 MT VERSUS 46.2 MT
* QTRLY AVERAGE REVENUE OF US$122/DRY METRIC TONNE
* QTRLY C1 COSTS OF US$12.81/WET METRIC TONNE
* DRILLING ACTIVITY HAS RECOMMENCED IN ARGENTINA AND IS EXPECTED TO RESTART IN ECUADOR IN Q3 FY21, SUBJECT TO COVID-19 RESTRICTIONS
* WHIMS PLANT THROUGHPUT IS FORECAST TO RAMP UP TO ITS INSTALLED CAPACITY AND EXPECTED YIELD IN H2 FY21
* TOTAL INVESTMENT IN ELIWANA PROJECT EXPECTED TO BE ABOUT US$1.375 BLN