* LNG plant machinery must typically be cooled ahead of start-up

* Cargo could also be 1st export shipment in case of more delays

* Ichthys has seen several delays, cost overruns

* Condensate to be exported before LNG

By Jessica Jaganathan and Osamu Tsukimori

SINGAPORE/TOKYO, April 23 (Reuters) - Japan's Inpex Corp and its partners have bought a cargo of liquefied natural gas (LNG) to cool their Ichthys LNG plant in Australia ahead of a potential start-up of the much delayed facility, a company spokesman said on Monday.

To produce LNG, natural gas is cooled down to around minus 160 degrees Celsius, so facilities must be chilled before production can begin, typically by using fuel from other sites. Taking such a step indicates the plant, in northern Australia's Darwin, is getting closer to starting output.

The LNG tanker 'Pacific Breeze' is currently in the Java Sea and expected to reach Darwin on April 26, with a draft of 93 percent, suggesting it is almost full, according to Thomson Reuters Eikon ship tracking data. The ship has the capacity to carry up to 182,000 cubic metres of LNG, according to Inpex.

A spokesman for Inpex 1605.T said the vessel had been chartered to transport LNG bought from another LNG project with the objective of cooling the onshore Ichthys LNG plant ahead of the project's start-up.

He added the vessel's LNG could also possibly be used as a first export cargo should Ichthys experience further delays in production, but stressed this had not yet been decided.

The more than $37 billion Ichthys project has seen several delays and cost overruns of billions of dollars due to technical difficulties. Japan's top oil and gas producer, said in March it had postponed its latest planned start-up to April or May. The start was originally slated for 2016. newly-built Pacific Breeze is contracted to supply 1.75 million tonnes a year of LNG from Ichthys to Taiwan's CPC Corp.

CPC did not respond to queries for comment.

The vessel loaded a cargo in Singapore in late March after conducting sea trials.

Once the Central Processing Facility is commissioned at Ichthys, it will produce condensate - an ultra-light form of crude oil - before LNG, Inpex has said without giving a specific timeframe.

Taiwan's CPC, the biggest customer of Ichthys, is scheduled to take delivery of its first LNG cargo in the second half of this year, a source familiar with the matter said, declining to be identified.

Other customers of the project mainly include Japanese utilities.

Inpex holds 62.245 percent of Ichthys, France's Total TOTF.PA 30 percent, with the rest spread amongst Taiwan's CPC Corp CHIP.UL and Japanese utilities Tokyo Gas 9531.T , Osaka Gas 9532.T , Kansai Electric 9503.T , JERA Corp and Toho Gas 9533.T .

Exports from new LNG projects including Ichthys are expected to help Australia overtake Qatar to become the world's largest exporter of the super-chilled fuel by 2019.

<^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ Interactive Map

reuters://REALTIME/verb=Interactive%20Map/context=%3CNavigation%3E%3CEntities%3E%3CEntity%20type= 'archive'%3E%3CIMap%3EtwIAAB+LCAAAAAAABACdUltrwjAYfR/sP4T8AGNv1o 40MCo4WYXh6m5vwX7WME1KUgUf9t+XdhVbNzbYQ24n3znfOSR0JivQfFWJA8x5iQ 6gjVAyxg5m1ALNlHFdQPWm1I55lPSB830CtRR6sVwnGESO63qOH2D0agF/4DlhEP ljHyPScOYqB+Y2as2WPmte3mq1lznL9B4o6QA05UdrrF1RdiwhxksDOhWmskYfYQ s2gpKMLmYJSz7u09AbRqPIHYUhJTVGSadolluvYi1qzesrhDoAknwHpuQr28HysB WbTmux0A9GY2v4XPoXFX11hDzG+Junnkz3aFOSJmY/7RMYA1uT2bd6N/+I3BAhb2 V+I11WJkquRbHXvCOUgiyqDZssFzcP0XDSklqU3olis7Wj+qlJ75KSC/VTdHJ6cd J8QtL/puwT7v8k2bcCAAA=%3C/IMap%3E%3C/Entity%3E%3C/Entities%3E%3C /Navigation%3E MAP: Ichthys LNG export facility to receive LNG cooling cargo

https://reut.rs/2F95xNf

^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^>

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.